Quadro Services Ltd v Creagh Concrete Products Ltd: TCC 28 Sep 2021

Enforcement of adjudication – The Defendant resists enforcement on the ground that the Adjudicator had no jurisdiction because three disputes were referred to him. It is settled law that an adjudicator does not have jurisdiction to adjudicate more than one dispute in a single adjudication.

Her Honour Judge Sarah Watson
[2021] EWHC 2637 (TCC)
Bailii
England and Wales

Arbitration

Updated: 02 November 2021; Ref: scu.668322

Harbour General Works Ltd v Environment Agency: 2000

References: [2000] 1 Lloyd’s Rep 65
Ratio:
Jurisdiction: England and Wales
This case is cited by:

  • Mentioned – Cetelem Sa v Roust Holdings Ltd CA (Bailii, [2005] EWCA Civ 618, Times 13-Jun-05, [2005] 1 WLR 3555)
    The parties were engaged in arbitration proceedings. The claimant had sought and obtained an interim mandatory order intended to prevent the defendant dissipating its assets in anticipation of an adverse ruling. The defendant sought leave to appeal. . .

(This list may be incomplete)

Last Update: 15 June 2020
Ref: 226190